Roberts Library Construction 2024-2025: Timelines

Phase 1

Feb. 3 - Start of Renovation

Phase 1 - 2nd Floor 

  • demo of two offices on 2nd floor - Advising area
  • demo of restrooms
  • demo of entrance to restrooms
  • demo of central stairwell (2nd floor) 
  • demo of stairwell - west wing
  • framing of Student Success & Advising office suite
  • removal of ceiling tile for HVAC and lighting work
  • installation of new PICU units and lighting
  • reinstallation of ceiling tile and lighting fixtures
  • installation of new restroom fixtures and finishes
  • drywall on Advising offices & suite area
  • new exterior entrance and stairwell
  • installation of carpet, flooring, and painting in new areas

May 31- End of Phase 1

Phase 2

June-July - Phase 2 - 1st Floor 

  • demo of central stairwell 
  • demo of 3 offices 
  • demo of restrooms 
  • demo of ceiling tile for HVAC and lighting work
  • reinstallation of ceiling tile and lighting fixtures
  • demo of some flooring areas
  • framing of new cafe, study rooms, offices, and collaborative spaces
  • installation of new restroom fixtures and finishes
  • installation of central stairwell
  • installation of carpet, flooring and painting in new offices/areas. 

Spring 2026 - Grand Opening