Skip to Main Content

Roberts Library Construction 2024-2025: 2nd floor Progress

Stairwell Across from the Circulation Desk

Drywall removed

Brick removed

Wall removed

Sidewall coming down

Original windows found.

Prior to 2002 these were exterior windows

Walls and glass removed

Window frames removed

Stairwell opened up

Advising Area

Removing carpet

Framing new offices

Walls going up

Drywall

New paint

Area outside Advising

Inside Advising area

Other areas

Working on new ceiling tiles and lights

Removing the old, original elevator

No more old elevator

Carpet removed and new columns

New lighting and paint

New doors for the restrooms

Old door blocked up

New restrooms so far

New light fixture

New carpet in study area